You are here: EIC Ltd > Case Studies > EBS Case Studies > Castle Hill Hospital
Project Value: £1.15 million
Project Duration: 38 Weeks
Main Contractor: Barr Construction
Consultant: Donald Smith, Seymour & Rooley
Business Sector: Medical Facilities
This P.F.I. project involved the complete installation of electrical services to the new Phase 5 Building´ at Castle Hill Hospital, Hull.The two-storey building includes Radiology, Urology, Endoscopy and Out Patients Departments together with a new Administration block on the first floor.
The electrical installation comprises of new incoming sub-mains, LV switchboard and distribution boards throughout the building. Also included was the complete installation of lighting and emergency lighting small power nurse call.
This was a very successful project which was programmed to suit the Client´s phased relocation to each of the new departments without disruption to the existing hospital operations.