Project Value: £3.8 million
Project Duration: 32 Weeks
Main Contractor: Simpson (York) Ltd
Consultant: ACDP
Business Sector: Retail
A new Marks and Spencer store, built within the Westfield´s development centre comprising of 103,000 ft. The 5 storey building is fed from two 1600kVA 400V transformers and a 1000kVA generator to supply the essential services.
Services included incoming transformers/panels and LV switch panels, general lighting and power, emergency lighting, fire alarm, CCTV, intruder & access control, IT, mechanical power/control wiring and lightning protection.
Whilst the project had difficulties due to the demanding programme and new concepts to the original design standards, the store opened on schedule.