Tesco, Workington

Tesco Store, Workington Contact Us

Project Value: £280k
Project Duration: 7 days
Main Contractor: Johnson Construction
Consultant: N/A
Business Sector: Retail & Fast Track

Project Description

EIC completed the complete fit-out of the new build temporary store within 7 days, including externals. The temporary store will primarily serve people from the Northside and Seaton areas of Workington, as well as those out along the coast to Flimby and Maryport, who face a major detour to get into Workington town centre since the floods destroyed or closed the road bridges over the River Derwent.

Scope of works

The electrical crew started the install which consisted of 34 men split between a night and day crew commencing on the containment, fire alarm, lighting installation, small power, mains distribution and externals i.e. car park lighting, gantry signs.

The mechanical crew, consisting of a further 14 men split between nights and days installed all of the mechanical services in the building which consisted of air handling unit, LPHW pipe work/boiler plant, split AC systems to the sales floor and back of house areas, sanitary ware, above ground drainage and external services.

Project Overview

With strong management and a dedicated delivery team this high profile project was completed within a challenging timescale.

This was achieved by working closely with the main contractor and client and understanding the exact requirements of the contract.

This project was crucial to a local community Isolated because of the floodwater in November 2009.